top of page

Approved Submittals vs Contract Requirements: Why Installations Still Get Rejected on Federal Projects

Introduction

One of the most common disputes on federal construction projects occurs when installed work is rejected even though the contractor previously received an approved submittal for the material or system. Contractors sometimes assume that once a submittal is approved, the Government has accepted the proposed product and the installation cannot later be rejected.

Federal construction contracts do not operate this way.

Approval of a submittal does not modify the contract requirements, and installed work may still be rejected if it does not comply with the drawings, specifications, or referenced standards.

Understanding the distinction between submittal approval and contract compliance is essential for avoiding costly rework during construction.

The Submittal Process Verifies Proposed Compliance

Submittals are intended to provide documentation showing that the contractor’s proposed materials, equipment, and procedures appear to comply with the contract requirements.

Typical submittals include:

  • shop drawings

  • product data

  • material certifications

  • test reports

  • manufacturer installation instructions

These documents allow Government reviewers to evaluate whether the contractor’s proposed materials and systems appear consistent with the specifications before the work is installed.

However, submittal review does not transfer responsibility for contract compliance from the contractor to the Government.

Submittal Approval Does Not Change the Contract

Federal construction specifications clearly address this issue.

UFGS 01 33 00 – Submittal Procedures, paragraph 1.13 Submittal Approval, states:

“Approval of a submittal does not relieve the Contractor from responsibility for complying with the requirements of the contract documents.”

This provision means that even when a submittal is marked “approved” or “approved as noted,” the contractor remains responsible for ensuring that the work complies with the contract requirements.

If the installed work does not meet the specifications, the Government may require correction of the work regardless of the submittal status.

Why Approved Submittals Still Lead to Rejected Work

Several situations commonly lead to rejection of installed work even when an approved submittal exists.

The Submittal Did Not Match the Contract Requirements

In some cases, the submitted documentation may not fully comply with the contract requirements. If the discrepancy is not identified during submittal review, the contractor may install materials that ultimately do not meet the specifications.

Because the contract places responsibility for compliance on the contractor, the work may still be rejected.

The Installation Did Not Match the Approved Submittal

Another common issue occurs when the contractor installs a product or system differently than it was described in the approved submittal.

Even if the submittal itself was compliant, the installed work must match both the approved submittal and the contract requirements.

If the installation deviates from the approved documentation, the work may be rejected.

The Submittal Attempted to Introduce a Substitution

Contractors sometimes attempt to introduce alternative materials through the submittal process. However, substitutions are governed by FAR 52.236-5 – Material and Workmanship, which states that the determination of whether a substitute is acceptable rests in the judgment of the Contracting Officer.

Submittal approval alone does not authorize a substitution.

If a proposed product differs from the contract requirements and formal approval has not been granted by the Contracting Officer, the installed work may be rejected.

The Government’s Right to Reject Non-Compliant Work

Federal construction contracts give the Government authority to reject work that does not comply with the contract requirements.

FAR 52.246-12 – Inspection of Construction, paragraph (f), states:

“The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements.”

This clause allows the Government to require removal and replacement of non-compliant work, even if the associated submittal had previously been approved.

Practical Guidance for Contractors

Contractors can avoid many submittal-related disputes by carefully verifying that their proposed materials and installation procedures comply with the contract requirements before submitting documentation for review.

Important practices include:

  • reviewing specifications carefully before preparing submittals

  • verifying that proposed products match the specified requirements

  • confirming that installation procedures comply with the specifications

  • requesting clarification when contract documents appear inconsistent

Submittal approval should be viewed as verification that documentation appears compliant, not as authorization to deviate from the contract requirements.

Conclusion

Federal construction contracts make clear that submittal approval does not modify the contract requirements or transfer responsibility for compliance to the Government.

Even when a submittal is approved, the contractor remains responsible for ensuring that materials, equipment, and installation procedures comply with the drawings, specifications, and referenced standards.

Understanding this distinction helps contractors avoid costly rework and ensures that construction activities remain consistent with the contract requirements.

Recent Posts

See All

Comments


Revised logo.png

DUNS# 021698908 | Cage Code 8E1M9

ISBEE 

©2005 by AftermathCompany.com 

bottom of page