top of page

What Happens After a Cure Notice on a Federal Construction Contract

Federal construction contracts provide the Government with several mechanisms for addressing contractor performance issues. One of the most significant of these mechanisms is the Cure Notice. Contractors sometimes misunderstand what a Cure Notice represents and how it affects the contract.

A Cure Notice is a formal communication issued by the Government when the Contracting Officer believes that the contractor’s performance places the contract in danger of termination for default. The notice provides the contractor an opportunity to correct the identified problems before more severe contractual action is taken.

Understanding the purpose and consequences of a Cure Notice is critical for contractors performing federal construction work.

The Contractual Basis for Cure Notices

Cure Notices arise from the Government’s authority under FAR 52.249-10 — Default (Fixed-Price Construction).

This clause provides the Government the right to terminate a construction contract for default if the contractor:

  • fails to prosecute the work with sufficient diligence to ensure completion within the contract time

  • fails to complete the work within the time specified in the contract

  • fails to perform other provisions of the contract

Before termination for default occurs, the Contracting Officer may issue a Cure Notice if there is sufficient time remaining in the contract schedule for the contractor to correct the problem.

What a Cure Notice Means

A Cure Notice signals that the Government believes the contractor’s performance is seriously deficient.

The notice typically identifies specific issues such as:

  • failure to maintain progress toward completion

  • failure to comply with contract requirements

  • inadequate quality control procedures

  • failure to correct deficient work

  • failure to comply with safety requirements

The notice gives the contractor an opportunity to explain how the deficiencies will be corrected.

Most Cure Notices provide the contractor 10 days to respond, although the exact response period may vary depending on the circumstances.

The Contractor’s Response

The contractor’s response to a Cure Notice is critical because it demonstrates whether the contractor can correct the performance issues identified by the Government.

A typical response should address:

  • the specific deficiencies identified in the notice

  • the cause of the performance problems

  • corrective actions that will be taken

  • a schedule showing how performance will be restored

The response should provide a clear plan demonstrating that the contractor can complete the work in accordance with the contract requirements.

Possible Outcomes After a Cure Notice

After reviewing the contractor’s response, the Contracting Officer evaluates whether the contractor has demonstrated the ability to correct the identified issues.

Several outcomes are possible.

Continued Performance

If the contractor’s response demonstrates that the problems are being addressed and that performance will improve, the Government may allow the contractor to continue work under the contract.

The project may proceed with increased monitoring of contractor performance.

Show Cause Notice

If the contractor’s response is inadequate or the performance issues continue, the Government may issue a Show Cause Notice.

A Show Cause Notice typically indicates that the Government is considering termination for default and gives the contractor an opportunity to explain why the contract should not be terminated.

Termination for Default

If the contractor fails to correct the performance issues identified in the Cure Notice, the Contracting Officer may terminate the contract for default under FAR 52.249-10.

Termination for default is one of the most serious actions the Government can take against a contractor because it may affect the contractor’s ability to obtain future federal contracts.

Why Cure Notices Are Issued

Cure Notices are not issued for minor administrative issues. They are generally used when the Government believes the contractor’s performance places successful completion of the project at risk.

Common reasons for Cure Notices include:

  • significant schedule delays

  • repeated quality deficiencies

  • failure to implement required quality control procedures

  • safety violations affecting project performance

The purpose of the Cure Notice is to give the contractor a final opportunity to correct the issues before termination becomes necessary.

Preventing Cure Notices

Contractors can reduce the likelihood of receiving a Cure Notice by maintaining strong project management and quality control procedures.

Key practices include:

  • monitoring schedule progress carefully

  • maintaining an effective quality control program

  • addressing deficiencies promptly

  • communicating with the Government when issues arise

Early communication often helps resolve problems before they escalate into formal contract actions.

Conclusion

A Cure Notice is a formal warning that a federal construction contract may be in danger of termination for default. The notice provides the contractor with an opportunity to correct performance issues and demonstrate the ability to complete the work in accordance with the contract requirements.

Responding effectively to a Cure Notice requires identifying the causes of the performance issues and presenting a clear plan for restoring compliance with the contract.

Understanding how Cure Notices function helps contractors manage performance issues effectively and avoid more severe contract actions.

Recent Posts

See All

Comments


Revised logo.png

DUNS# 021698908 | Cage Code 8E1M9

ISBEE 

©2005 by AftermathCompany.com 

bottom of page